Stage Two Construction Updates

We are delighted to share with you the latest update of our building progress by Glenvill Projects for the next stages of La Dimora Retirement Resort in the heart of the Mitchell Shire at Hidden Valley Resort.

The month of March has been a busy time for the site team with milestones achieved including:

  • Completion of all underground services

  • Commencement of services rough-in works

  • Completed roof tiles works to 3 villas

  • Completion of slabs, timber framing and roof trusses to 13 villas

  • Completed installation of windows and sliding glass doors to 10 villas

Internal plasterboard works have commenced, and the remaining 8 slabs for stage two should all be poured within three weeks. Hebel panels (external cladding) installation will commence shortly and wall timber framing and roof trusses are on track to be completed by the end of April.


Here are a few photos of the building progress:




With stage two at near completion, expressions of interest are now being taken for stages three and four however there’s no need to wait until you move in, come and bask in all of its glory today on the 18 hole championship golf course, well equipped Sports Hub including tennis, indoor pool & bowls, the fabulous Grove Bar and Bistro (open 7 days per week) all in a beautiful country setting.

If you would like to take a closer look at the exciting construction updates in person, or put in an expression please do not hesitate to make an appointment– call our team on 1300 098 098 or book online, click here.