Construction Update May 2022

Updated: May 10

We are delighted to announce stage two is now complete with all external works finalised.

Further developments:

Stage two: Landscape & asphalt works completed


Stage two: Fences & gates completed


Stage three is moving along with great momentum with a goal to achieve lock-up status for 18 Villas at the end of this month. We are pleased to have achieved the following milestones in the month of April:

  • Completion of shaft liner works for all villas

  • Completion of framing works for all villas

  • Roof trusses completed to 18 villas

  • Roof plumbing works completed for 18 villas

  • Installation of windows and sliding doors completed for 18 villas

  • Roof tile works completed for 11 villas

  • Services rough-in works completed for 12 villas

  • External cladding works completed for 12 villas

  • Commenced internal insulation and plasterboard works

  • Commenced installation of kitchen joinery

  • Commenced water-proofing works to wet areas

  • Commenced installation of solar panels

Stage three: Southern works in process


Stage three: Completion of framing works

Earthworks are due to start in stage four before the winter weather begins with the civil works contractor now appointed.


We look forward to sharing with you more exciting progress in next month's La Dimora updates.