Construction Update May 2022
Updated: May 10
We are delighted to announce stage two is now complete with all external works finalised.
Further developments:

Stage two: Landscape & asphalt works completed

Stage two: Fences & gates completed
Stage three is moving along with great momentum with a goal to achieve lock-up status for 18 Villas at the end of this month. We are pleased to have achieved the following milestones in the month of April:
Completion of shaft liner works for all villas
Completion of framing works for all villas
Roof trusses completed to 18 villas
Roof plumbing works completed for 18 villas
Installation of windows and sliding doors completed for 18 villas
Roof tile works completed for 11 villas
Services rough-in works completed for 12 villas
External cladding works completed for 12 villas
Commenced internal insulation and plasterboard works
Commenced installation of kitchen joinery
Commenced water-proofing works to wet areas
Commenced installation of solar panels

Stage three: Southern works in process

Stage three: Completion of framing works
Earthworks are due to start in stage four before the winter weather begins with the civil works contractor now appointed.
We look forward to sharing with you more exciting progress in next month's La Dimora updates.